Sanofi Pasteur
Sanofi Pasteur
MS Project Server 2003 Implementation
Customer Sanofi Pasteur, the vaccines business of
sanofi-aventis Group, is the largest company in the world
devoted entirely to human vaccines. Today Sanofi Pasteur is
present:
- in North America (US, Canada and Mexico)
- in Western Europe, in 19 countries, through Sanofi
Pasteur MSD, a 50/50 joint venture between Sanofi Pasteur
and Merck & Co.
- throughout the rest of the world, especially in Latin
America and countries in Eastern Europe and the Middle East,
as well as China and Japan.
Challenge
Sanofi Pasteur’s North American IT
Department needed to upgrade their project management tools from
MS Project Central to MS Project Sever 2003. This migration was
driven by a need to improve data integrity and streamline status
reporting and data analysis.
Approach
Using the Microsoft Implementation
Framework for EPM, Agora guided Sanofi Pasteur through the
implementation of MS Project Server 2003 and the migration of
existing project data into the new environment.
Solution
The new implementation provided the North
American IT Department with one resource pool from which to draw
resources for projects, consistent status and time reporting for the
department and reliable usage and progress reporting for management.
The implementation of templates and Project Guides also gave Sanofi
Pasteur a consistent starting point for launching every project.
Impact
Sanofi is now able to capture and analyse
project performance, resource usage and efficiency. Projects are all
initiated using the same template to ensure consistency. The PMO is
now capturing and analyzing key performance indicators using the
data captured in Project Server. This data is helping to make them
more effective in their resource deployment and project delivery.
|
|
Implement MS Project Server 2003
to replace MS Project Central.
Agora designed and implemented MS
Project Server 2003, migrating existing data from
Project Central.
Sanofi Pasteur’s North American
IT department has a consistent method for launching new
projects, managing time and status and is now capturing
key performance indicators on resource usage. |
|
|
Sanofi Pasteur |
|